| |
KIHEI EFFLUENT REUSE SYSTEM County of
Maui
(page 2 of 3)
< Go to page 1
New
improvements included in the Core System project were designed to
operate in concert with the existing facilities, and are also
capable of functioning under expanded operating conditions as the
plant capacity is increased in the future. The new improvements include a 1.0 million gallon
reinforced concrete reservoir constructed with an aluminum
geodesic dome cover, and an 18-inch ductile iron pipeline to
connect the reservoir to the reclamation facility. |

1.0 Million Gallon Concrete
Reservoir |
The dome cover eliminated the need for interior columns and
footings within the reservoir, and the resulting cost savings
allowed for the installation of a high quality tank lining system. The storage and transmission system is also equipped with
remote pressure and flow sensors and level controls that
communicate with the Kihei WWRF control station. Due to the reservoir’s remote location, level sensors at
the tank utilize solar powered radio transmitters to communicate
with the WWRF control station, thus eliminating the need for
conventional power and communication lines. The telemetry system
enables system operation and status checks through the plant’s
Supervisory Control and Data Acquisition (SCADA) System.
|
The Core System was put into operation prior to
being fully completed so that it could continue to serve Monsanto
Corporation’s seed corn operations and the Elleair Golf Course. Cooperation between effluent consumers, the County and the
Contractor, Hawaiian Dredging Construction Company, allowed
virtually uninterrupted service during the construction period. The total project construction cost for the Kihei Effluent
Reuse Core System was $3.2 million. Total project construction time was 12 months with the
project substantially completed in April 1998. |

Monsanto Corporation
seed corn field |
Kihei Effluent
Reuse Distribution System, Phase I
|
Community interest in utilizing reclaimed
effluent and the surplus funding available from the initial project
prompted the County to extend the effluent distribution capability of
the Kihei Effluent Reuse Core System. The Kihei Effluent Distribution System, Phase I was initiated
during the construction phase of the Core System. Planning, design and bidding of the project was accomplished
prior to the completion of construction for the Effluent Reuse Core
Project. One of the
goals of the project was to complete construction of the distribution
system before to the completion of the Kihei Community Center,
allowing the effluent to be used for the establishment of the
playfields being constructed at the Center. |

Kihei Community
Center Playfield |
Go
to page 3 > |
|